Workshop & Surat Perintah Kerja (SPK)

Overhaul Engine SAA6D140E / CAT C15, Rebuild Silinder Hidrolik & Field Break Down

SPK-WRK/2026/08/0055

Komatsu Excavator PC400-8 (Unit EX-412)

PT. Pamapersada Nusantara (PAMA)
Dyno Test & Calibration
Pekerjaan: Major Engine Overhaul (SAA6D140E-5)
Lokasi: Workshop Utama Kariangau (Bay 3)
Lead Mekanik: Agus Setiawan (POP K3 Certified)
Timeline: 2026-08-15 s/d 2026-08-28
Estimasi Biaya: Rp 148.500.000
Progres Pengerjaan 85%
SPK-WRK/2026/08/0052

Caterpillar Off-Highway Truck CAT 777D (Unit DT-708)

PT. Kaltim Prima Coal (KPC)
Final QC & Pressure Test
Pekerjaan: Rebuild Dual Hoist & Steering Cylinder
Lokasi: Workshop Utama Kariangau (Bay 1)
Lead Mekanik: Budi Hartono (Master Hydraulic)
Timeline: 2026-08-18 s/d 2026-08-26
Estimasi Biaya: Rp 64.000.000
Progres Pengerjaan 95%
SPK-WRK/2026/08/0049

Hitachi Excavator ZX470-5G (Unit EX-092)

PT. Berau Coal
Completed / Unit Commissioned
Pekerjaan: Emergency Field Service: Main Pump Replacement
Lokasi: Pit Binungan Site Berau (Field Deployment)
Lead Mekanik: Rian Pratama (Field Specialist)
Timeline: 2026-08-20 s/d 2026-08-23
Estimasi Biaya: Rp 38.500.000
Progres Pengerjaan 100%
SPK-WRK/2026/08/0046

Komatsu Bulldozer D85ESS-2 (Unit DZ-105)

PT. Bukit Makmur Mandiri Utama (BUMA)
In Progress (Pin Pressing)
Pekerjaan: Undercarriage Pin & Bushing Turn & Track Alignment
Lokasi: Workshop Utama Kariangau (Bay 4)
Lead Mekanik: Surya Wijaya (Undercarriage Tech)
Timeline: 2026-08-22 s/d 2026-08-29
Estimasi Biaya: Rp 52.000.000
Progres Pengerjaan 45%